關(guān)鍵詞:高層建筑;給排水工程;控制要點(diǎn)
Abstract: With the deepening of reform and opening-up, built many tall buildings. In the high-rise building engineering, water supply and drainage engineering as a supporting project, its construction quality has great influence on the engineering performance of the play. Building water supply and drainage supervision engineering should be built in to ensure the engineering quality as the goal, several construction process quality, process as the core, good drainage and supervision of the work of building. The main problem, in this paper, building water supply and drainage engineering supervision the quality of water supply and drainage construction control is weak, and the supervision quality control key points are introduced.
Key words: high-rise building water supply and drainage engineering; control points;
中圖分類號(hào):TU99 文獻(xiàn)標(biāo)識(shí)碼: 文章編號(hào)
隨著社會(huì)的發(fā)展,城市建筑用地越來(lái)越少,建筑技術(shù)水平日益提高,越來(lái)越多的高樓大廈出現(xiàn)在人們的視線里,城市建筑在向高層方向發(fā)展。然而,給排水工程作為城市建筑的配套工程,其好壞與工程的使用功能的發(fā)揮息息相關(guān)。施工前準(zhǔn)備、施工過(guò)程到所形成的產(chǎn)品質(zhì)量都是給排水工程實(shí)際施工監(jiān)理過(guò)程中極其重要的控制環(huán)節(jié)。
一、建筑給排水工程監(jiān)理面臨的主要問(wèn)題
雖然從工程量和投資角度上來(lái)看,高層建筑安裝工程中的給排水分部比較少,但卻在建筑產(chǎn)品的質(zhì)量投訴中相當(dāng)大的比例。這些質(zhì)量問(wèn)題不會(huì)在建筑主體的施工階段發(fā)生,但卻與其有著必然的聯(lián)系。
在主體結(jié)構(gòu)施工階段,由于給排水工程的施工主要是預(yù)留和預(yù)埋,工程量較小,因此從領(lǐng)導(dǎo)至項(xiàng)目負(fù)責(zé)人都普遍對(duì)此階段的重視程度偏低。因而,產(chǎn)生了大量位置不準(zhǔn)的預(yù)留洞和預(yù)留套管,甚至出現(xiàn)漏埋套管和漏留洞口的現(xiàn)象,這無(wú)疑給工程帶來(lái)了質(zhì)量缺陷和事故隱患。出現(xiàn)這些問(wèn)題后,施工者在管道及設(shè)備安裝時(shí),往往選擇直接在樓板、剪力墻上鑿洞,造成建筑主體結(jié)構(gòu)面目全非,坑坑洼洼,得不償失,不僅浪費(fèi)了大量的人力和物力,還使得衛(wèi)生間樓板等結(jié)構(gòu)的承載能力大大降低;也不乏出現(xiàn)這樣的現(xiàn)象,在不能鑿打梁柱的情況下勉強(qiáng)安裝原來(lái)的預(yù)留洞,不僅給外觀帶來(lái)不可修補(bǔ)的遺憾,還可能留下漏水的隱患。其實(shí),給排水工程的施工在建筑主體施工階段是一個(gè)非常關(guān)鍵的內(nèi)容,其施工質(zhì)量的好壞一方面對(duì)整個(gè)給排水分部工程的質(zhì)量造成了直接影響,另一方面,對(duì)于住宅整體的質(zhì)量和安全也帶來(lái)了不可忽視的影響。如果監(jiān)理工程師對(duì)此引起足夠的重視,并采取相應(yīng)的可靠措施,保證給排水工程的施工的質(zhì)量,就能避免出現(xiàn)上述情況。
二、給排水工程監(jiān)理質(zhì)量控制要點(diǎn)
1.工程施工前期階段
(1)認(rèn)真擬定所監(jiān)理項(xiàng)目的給排水專業(yè)細(xì)則,并切實(shí)按此細(xì)則指導(dǎo)項(xiàng)目監(jiān)理。
(2)了解施工單位的管理水平和技術(shù)水平,認(rèn)真審核承包商提交的施工組織設(shè)計(jì),加強(qiáng)預(yù)控力度。
(3)組織有效的施工圖交底與會(huì)審,給排水監(jiān)理工程師工作的重點(diǎn)應(yīng)在:1)弄清住宅的裝修水準(zhǔn),如果是初裝,監(jiān)理工程師應(yīng)明白衛(wèi)生間、廚房給排水支管是否要求統(tǒng)一安裝等;2)檢查承包商專業(yè)技術(shù)人員的配備情況,并要求承包商提前提交圖紙會(huì)審情況;3)給排水監(jiān)理工程師仔細(xì)審圖,及時(shí)將施工圖中的有關(guān)問(wèn)題及業(yè)主、承包商提交的圖紙會(huì)審意見整理成文,提前提交設(shè)計(jì)單位,以便設(shè)計(jì)單位在圖紙會(huì)審時(shí)有充分的準(zhǔn)備;4)及時(shí)協(xié)調(diào)解決會(huì)審中有關(guān)各方提出的技術(shù)問(wèn)題,確保項(xiàng)目施工如期開展。
2.施工中的監(jiān)理
監(jiān)理工程師應(yīng)跟蹤檢查排水系統(tǒng)的排出管及給水系統(tǒng)引入管穿越建筑物基礎(chǔ)處、地下室或地下構(gòu)筑物外墻處,確保其按設(shè)計(jì)及施工規(guī)范要求設(shè)置了合格的套管并且預(yù)留了孔洞,一般對(duì)于有嚴(yán)格防水要求的地方,需要采用柔性防水套管,而一般防水要求的則采用剛性防水套管,針對(duì)無(wú)防水要求的采用設(shè)預(yù)留孔的方法即可。管道安裝完成后,須確保其上部?jī)艨詹坏眯∮诮ㄖ锏某两盗?,一般?lái)說(shuō)150mm是最低極限值。在施工單位安裝完成埋地的給排水管道后,再完成首層室內(nèi)地面回填及搗制混凝土的工作,在這里,需引起注意的是要確保對(duì)照?qǐng)D紙及伸出地面管道的垂直度無(wú)遺漏且安裝位置滿足現(xiàn)場(chǎng)要求。
(1)為確保無(wú)誤,須對(duì)相關(guān)設(shè)備基礎(chǔ)、預(yù)埋件、預(yù)留孔(洞)進(jìn)行、檢查和復(fù)測(cè)。
(2)檢查并確保檢查工藝流程和施工技術(shù)滿足設(shè)計(jì)規(guī)程。
(3)在強(qiáng)度和嚴(yán)密性試驗(yàn)完畢后再進(jìn)行閥門的安裝。
(4)檢查并確保管道的連接符合規(guī)范的要求以及管道上使用的壓制彎頭、彎頭的外徑與管道的外徑相同。
(5)對(duì)于有管道穿過(guò)的地下構(gòu)筑物外墻或地下室,必須采取相應(yīng)的防水措施;若建筑物有嚴(yán)格的防水要求,必須采用柔性防水套管。
(6)禁止在墻內(nèi)或樓板內(nèi)設(shè)置管道的接頭或焊接,對(duì)于暫時(shí)不接的管口需用堵頭堵好。
(7)對(duì)給水、排水管道的坡向、坡度進(jìn)行檢查,確保其符合設(shè)計(jì)及規(guī)范要求。
(8)對(duì)管道吊架、支架、管卡進(jìn)行檢查,確保其符合設(shè)計(jì)或規(guī)范要求。
(9)對(duì)各種非承壓管道系統(tǒng)和設(shè)備進(jìn)行灌水試驗(yàn),承壓管道系統(tǒng)和設(shè)備做水壓試驗(yàn)。
(10)協(xié)助業(yè)主對(duì)設(shè)備配件材料的購(gòu)置進(jìn)行嚴(yán)格的控制,并核對(duì)材料規(guī)格以設(shè)備型號(hào),對(duì)于供貨商的供貨能力、供貨期限、以及信譽(yù)等進(jìn)行嚴(yán)格的審核。
(11)施工單位在工序交接過(guò)程的檢查中,要求通過(guò)自檢、專檢后對(duì)檢查批質(zhì)量驗(yàn)收單進(jìn)行填寫,下一道工序的進(jìn)行前必須確保報(bào)監(jiān)理檢查合格并且簽證。
(12)對(duì)于重要的工序要做好及時(shí)控制與預(yù)控相結(jié)合。
(13)不合格的工程不予計(jì)量。
(14)隱蔽工程在隱蔽前,應(yīng)做好相應(yīng)的各項(xiàng)試驗(yàn),確保其嚴(yán)查合格。
(15)應(yīng)對(duì)突發(fā)的工程事故,通報(bào)甲方,由甲方發(fā)出停止指令,停止后及時(shí)對(duì)事故原因進(jìn)行分析,并重新進(jìn)行試驗(yàn)、檢查、驗(yàn)收。
(16)施工單位須嚴(yán)格按“主控項(xiàng)目”和“一般項(xiàng)目”的相關(guān)規(guī)定執(zhí)行,并簡(jiǎn)明、真實(shí)、清晰地填寫相關(guān)資料。
3.工程驗(yàn)收階段
(1)工程竣工前,為保證器具、箱等其表面清潔,內(nèi)部沒(méi)有污物,應(yīng)全面清理所有的水表、閥門、衛(wèi)生器具、消火栓等設(shè)施。
(2)對(duì)給水管道的水壓試驗(yàn)、閥門的試壓、給水系統(tǒng)的吹洗、通水試驗(yàn)、排水管道的灌水試驗(yàn)等進(jìn)行檢測(cè),并對(duì)項(xiàng)目的測(cè)試及測(cè)試報(bào)告的編制進(jìn)行測(cè)試,對(duì)各種給排水技術(shù)資料、所有隱蔽工程檢查的隱蔽單、質(zhì)保證書、合格證書、材料的測(cè)試報(bào)告及各種電器等進(jìn)行整理匯總,裝訂成冊(cè)。工程竣工圖作為工程驗(yàn)收的依據(jù)和建設(shè)單位今后維修的原始資料,需要根據(jù)工程實(shí)際的施工情況進(jìn)行編制,整理匯總并裝訂成冊(cè)。
給排水系統(tǒng)對(duì)結(jié)果進(jìn)行驗(yàn)收的根據(jù)除了水壓試驗(yàn)、外觀檢查、灌水試驗(yàn)和通水試驗(yàn)的結(jié)果外,還有如下幾點(diǎn)需注意。
管道工程的質(zhì)量檢查如下:
①檢查管道的平面位置、坡向、標(biāo)高、管材、管徑,確保其符合要求
②檢查支架、管道、衛(wèi)生器具的位置及安裝的牢度程度,確保其符合要求。
③檢查水表、閥件、水泵等的安裝,確保沒(méi)有漏水現(xiàn)象,對(duì)于衛(wèi)生器,確保其排水通暢。
④對(duì)管道油漆和保溫進(jìn)行檢查,確保其符合設(shè)計(jì)要求。應(yīng)按檢驗(yàn)批、分部、分項(xiàng)或單位工程對(duì)給排水工程進(jìn)行驗(yàn)收,對(duì)其進(jìn)行驗(yàn)收和質(zhì)量評(píng)定必須要按國(guó)家有關(guān)規(guī)范和標(biāo)準(zhǔn)進(jìn)行。
驗(yàn)收工程時(shí),施工單位需提供如下資料:
①制品、設(shè)備和主要材料的試驗(yàn)記錄或合格證;
②竣工圖、施工圖和有關(guān)變更文件;
③水壓試驗(yàn)記錄;
④隱蔽工程的中間試驗(yàn)記錄和驗(yàn)收記錄;
⑤設(shè)備試運(yùn)轉(zhuǎn)記錄;
⑥管道沖洗試驗(yàn)記錄;
⑦檢驗(yàn)批、分項(xiàng)、分部、單位工程質(zhì)量檢驗(yàn)評(píng)定記錄等。
⑧工程質(zhì)量事故處理記錄;
三、結(jié)束語(yǔ)
建筑給排水工程的監(jiān)理工程師要嚴(yán)格按照施工規(guī)范和設(shè)計(jì)圖紙的要求,在施工節(jié)點(diǎn)、施工工序、工程驗(yàn)收過(guò)程中重點(diǎn)控制,針對(duì)給排水工程施工質(zhì)量中較薄弱環(huán)節(jié),監(jiān)理要格外注意,保證施工質(zhì)量,使給排水工程達(dá)到節(jié)省空間、使用方便、經(jīng)久耐用和美觀舒適的效果。
參考文獻(xiàn):
[1]林江濤.淺談建筑給排水施工監(jiān)理[J].科技創(chuàng)新導(dǎo)報(bào) 2008(16).
關(guān) 鍵 詞: 建筑給排水 施工監(jiān)理 質(zhì)量控制
中圖分類號(hào):S276文獻(xiàn)標(biāo)識(shí)碼:A 文章編號(hào):
Abstract:Water supply and drainage engineering construction and acceptance of supervision and management, aims to correct supervision means to promote the reasonable construction, ensure the construction quality. This paper discusses the construction of supervision work, and mainly from the construction process in water supply engineering, fire engineering and drainage works on three aspects of the supervision quality control.
Key Words:Building water supply and drainage; Construction supervision; Quality control
引 言
隨著人們的生活品質(zhì)的提高,對(duì)建筑給排水工程質(zhì)量的要求也越來(lái)越高,給排水工藝標(biāo)準(zhǔn)復(fù)雜程度越來(lái)越高,新材料、新工藝層出不窮,對(duì)建筑給排水工程質(zhì)量的要求也越來(lái)越嚴(yán)格,這樣對(duì)給排水工程的監(jiān)理工作也提出了更高的要求。其施工質(zhì)量的好壞直接決定了整個(gè)工程竣工交付后使用性能。因此如何在工程施工的各個(gè)環(huán)節(jié)嚴(yán)把質(zhì)量關(guān),將監(jiān)理工作的實(shí)質(zhì)落到實(shí)處是我們監(jiān)理最為關(guān)心的問(wèn)題。
1施工前期的監(jiān)理工作
在給排水工程的施工監(jiān)理過(guò)程中,包括施工前的材料準(zhǔn)備和施工過(guò)程中形成的產(chǎn)品質(zhì)量,都是重要的控制環(huán)節(jié)。
1.1做好圖紙會(huì)審
設(shè)計(jì)交底和圖紙會(huì)審是工程建設(shè)的一個(gè)重要環(huán)節(jié),對(duì)設(shè)計(jì)文件的充分了解是監(jiān)理工程師對(duì)工程質(zhì)量控制所必做的準(zhǔn)備工作之一。通過(guò)設(shè)計(jì)交底可以了解設(shè)計(jì)意圖,需要熟悉施工圖,清楚給排水管道室外和室內(nèi)的連接處,墻壁、樓板的位置標(biāo)高和安裝方案。了解工程的重點(diǎn)和難點(diǎn),通過(guò)圖紙會(huì)審可以發(fā)現(xiàn)和解決圖紙?jiān)O(shè)計(jì)中存在的問(wèn)題,看是否違背了相關(guān)規(guī)范等。并且這是解決給排水專業(yè)同其它專業(yè)之間的矛盾沖突,統(tǒng)一各方意見,為工程順利實(shí)施創(chuàng)造必要條件。在設(shè)計(jì)交底時(shí),對(duì)管線集中處,特別是人防工程和地上工程之間的管線布置,監(jiān)理應(yīng)重點(diǎn)控制,杜絕實(shí)際安裝時(shí)發(fā)生位置沖突等問(wèn)題。
1.2詳細(xì)審核施工組織的設(shè)計(jì)
在給排水的監(jiān)理工作中應(yīng)以監(jiān)理工程師為核心體系,確定監(jiān)管項(xiàng)目所需的技術(shù)措施和組織措施,在工程施工過(guò)程中按監(jiān)理細(xì)則實(shí)施工程項(xiàng)目的監(jiān)理。在工程開工之前必須將總承包商和各分包商的工程承包范圍劃分清楚,并把各個(gè)施工單位的質(zhì)量責(zé)任明確下來(lái)。
1.3對(duì)進(jìn)場(chǎng)材料的檢驗(yàn)要求
(1)在承包商對(duì)原材料、半成品和構(gòu)配件進(jìn)行采購(gòu)訂貨前,應(yīng)向監(jiān)理項(xiàng)目部進(jìn)行申報(bào);重要的材料,還應(yīng)當(dāng)提交檢驗(yàn)或鑒定的樣品,部分材料還要求供貨商提交物理和化學(xué)試驗(yàn)單,經(jīng)監(jiān)理項(xiàng)目部審查同意后,方可采購(gòu)。材料進(jìn)場(chǎng)時(shí)必須具備正式的出廠合格證和備案證;散熱器、閥門、水嘴、鑄鐵管件、排水硬聚氯乙烯管件管材、冷熱水用聚丙烯管材、管件必須復(fù)試;主要設(shè)備訂貨前,施工單位應(yīng)向監(jiān)理單位提出申請(qǐng),由監(jiān)理工程師核定是否符合設(shè)計(jì)要求;主要配件訂貨前,施工單位要提供樣品和有關(guān)訂貨廠家情況,經(jīng)研究同意后方可訂貨;在施工過(guò)程中隨時(shí)對(duì)工程中使用的材料進(jìn)行抽樣檢查,對(duì)不符合質(zhì)量要求的材料堅(jiān)決予以撤換。
(2)供應(yīng)商是制造材料、半成品、構(gòu)配件供應(yīng)的主體,所以通過(guò)實(shí)地檢查滿足要求的供應(yīng)商,是確保原材料、半成品和構(gòu)配件質(zhì)量的前提。同時(shí)對(duì)于大宗的器材或材料的采購(gòu),監(jiān)理項(xiàng)目部也應(yīng)要求承包商進(jìn)行公開招標(biāo)。
(3)對(duì)于材料、半成品、構(gòu)配件,在按照規(guī)定報(bào)經(jīng)批準(zhǔn)后,交付的時(shí)間應(yīng)滿足施工進(jìn)度的需要,不得無(wú)故拖延。
(4)供應(yīng)商應(yīng)向承包商提供質(zhì)量文件,以證明材料、半成品、構(gòu)配件能夠滿足的質(zhì)量要求。
(5)部分特殊材料,訂貨時(shí)最好一次備足貨源。
2施工過(guò)程中的監(jiān)理質(zhì)量控制
2.1室內(nèi)給水系統(tǒng)安裝工程
(1)施工工藝及監(jiān)理工作流程,(如圖一)。
圖一
安裝準(zhǔn)備,干管安裝,支管安裝,試壓、沖洗,設(shè)備、給水配件安裝,通水試驗(yàn)。
(2)施工要點(diǎn)控制:隱蔽管道和給水系統(tǒng)的水壓試驗(yàn)結(jié)果必須符合設(shè)計(jì)要求和施工規(guī)范規(guī)定。給水管道試驗(yàn)壓力不應(yīng)小于0.6 MPa ,各種材質(zhì)的給水管道系統(tǒng)試驗(yàn)壓力應(yīng)為工作壓力的1.5倍; 埋地管道管溝密實(shí)度必須符合設(shè)計(jì)要求或施工規(guī)范規(guī)定,管溝位置、標(biāo)高符合設(shè)計(jì)要求。嚴(yán)禁鋪設(shè)在未經(jīng)處理的松土上;給水引入管與排水排出管的水平凈距不得小于1米;立管、橫支管安裝應(yīng)先裝支托架,支托架的規(guī)格、型式、間距必須符合設(shè)計(jì)要求或施工規(guī)范規(guī)定;管道穿過(guò)基礎(chǔ)、墻壁和樓板,應(yīng)配合土建預(yù)留孔洞;埋地管道的防腐層應(yīng)符合設(shè)計(jì)要求和施工規(guī)范規(guī)定;飲用水管道在使用前應(yīng)用每升水中含20-30毫克的游離氯的水灌滿管道進(jìn)行消毒,含氯水在管中應(yīng)留置24小時(shí)以上。消毒完后,再用飲用水沖洗,并經(jīng)有關(guān)部門取樣檢驗(yàn)水質(zhì)未被污染,方可使用。
(3)施工過(guò)程中質(zhì)量通病的預(yù)防:托、吊、卡架不牢固。由于剔洞深度不夠,卡子燕尾被切斷,埋設(shè)卡架洞內(nèi)雜物未清理凈,砼封堵又不澆水,致使固定不牢;立管甩口高度不準(zhǔn)確。其原因是由于層高超出允許偏差或測(cè)量不準(zhǔn);立管距墻不一致或半明半暗。其原因是由于立管位置安排不當(dāng),或隔斷墻位移偏差太大造成;水流不暢或管道堵塞。其原因是安裝前未認(rèn)真清理管子內(nèi)部;施工過(guò)程中,管口未及時(shí)封堵或封堵不嚴(yán);水箱不及時(shí)加蓋,致使雜物落入堵塞或污染管道;不按規(guī)定進(jìn)行水壓試驗(yàn)和通水前的沖洗。
2.2室內(nèi)消防給水系統(tǒng)安裝工程
(1)施工工藝流程。
消防管道及設(shè)備安裝的操作流程,(如圖二)。
圖二
(2)施工階段控制要點(diǎn)
消火栓、噴淋頭安裝位置,應(yīng)嚴(yán)格依照設(shè)計(jì)圖紙要求執(zhí)行,噴淋頭成排、成行,與吊頂接觸牢靠,裝飾(護(hù)口)盤平正。消防系統(tǒng)試驗(yàn)壓力,須按設(shè)計(jì)要求確定。消防報(bào)警閥應(yīng)設(shè)在明顯、易于操作的位置,報(bào)警閥應(yīng)有排水措施。消防箱內(nèi)附件應(yīng)配置齊全,箱內(nèi)報(bào)警按鈕位置正確,聯(lián)動(dòng)靈敏。消火栓栓口應(yīng)朝外,閥門中心距地面以1.1米為宜。水流指示器安裝方向應(yīng)正確,動(dòng)作靈敏。噴淋系統(tǒng)各層、試水裝置應(yīng)設(shè)置在能便于排水的地方。安裝自動(dòng)噴灑消防裝置,應(yīng)不妨礙噴頭噴水效果。如設(shè)計(jì)無(wú)規(guī)定,應(yīng)符合下列規(guī)定:吊架與噴頭的距離,應(yīng)不小于300 毫米;距末端噴頭的距離不大于750 毫米;吊架應(yīng)設(shè)在相鄰噴頭間的管段上,當(dāng)相鄰噴頭間距不大于3.6 米,可設(shè)一個(gè),小于1.8 米允許隔段設(shè)置。閥門應(yīng)按施工規(guī)范要求做好強(qiáng)度和嚴(yán)密性試驗(yàn)。監(jiān)理工程師每日將監(jiān)理工作紀(jì)要記錄于《監(jiān)理日記》中, 對(duì)施工監(jiān)理過(guò)程中發(fā)現(xiàn)的不合格,簽發(fā)《監(jiān)理工程師通知書》要求施工單位及時(shí)整改,經(jīng)整改后確認(rèn)《監(jiān)理工程師通知回復(fù)單》。對(duì)需向業(yè)主專項(xiàng)說(shuō)明的事項(xiàng)及需確認(rèn)存證事項(xiàng)以《監(jiān)理工作聯(lián)系單》報(bào)送相關(guān)單位。
(3)質(zhì)量通病的防治
1)噴淋頭處有滲漏現(xiàn)象。由于尚未系統(tǒng)試壓就封吊頂,造成通水后滲漏。封頂前必須經(jīng)試壓。2)噴淋頭與吊頂接觸不牢。護(hù)口盤偏斜。3)由于支管末端彎頭處未加卡件固定,支管尺寸不準(zhǔn),使護(hù)口盤不正。4)噴淋頭不成排、成行。5)由于未拉線安裝。水流指示器工作不靈敏。6)由于安裝方向相反或電接點(diǎn)有氧化物造成接觸不良。7)水泵結(jié)合器不能加壓。由于閥門未開啟,單向閥裝反或有盲板未拆除造成。8)消火栓箱門關(guān)閉不嚴(yán)。由于安裝未找正或箱門強(qiáng)度不夠變形造成。9)消火栓閥門關(guān)閉不嚴(yán)。由于管道未沖洗干凈,閥座有雜物造成。10)消防管道安裝缺陷。其原因是消火栓口朝向不對(duì),標(biāo)高位置不準(zhǔn);水龍帶不按規(guī)定擺放。其原因是施工時(shí)沒(méi)有按規(guī)定安裝,施工安裝時(shí)不認(rèn)真。應(yīng)該在施工的過(guò)程中嚴(yán)格按照規(guī)定的施工要點(diǎn)來(lái)落實(shí)。
2.3室內(nèi)排水系統(tǒng)安裝工程
(1) 施工工藝流程,(如圖三)。
安裝準(zhǔn)備
干管安裝
支管安裝
潔具安裝
通水試驗(yàn)
圖三
(2)施工階段控制要點(diǎn)。
1) 隱蔽的排水和雨水管道的灌水試驗(yàn)結(jié)果,必須符合設(shè)計(jì)要求或施工規(guī)范規(guī)定。2) 排水管道坡度必須符合設(shè)計(jì)要求或施工規(guī)范規(guī)定。3) 排水立管應(yīng)按設(shè)計(jì)要求或施工規(guī)范規(guī)定設(shè)置檢查口,塑料管必須按設(shè)計(jì)要求裝設(shè)置伸縮節(jié)。4) 塑料排水管粘接時(shí),插入承口深度適宜,粘接均勻,管卡應(yīng)為塑制卡架,若用鋼制卡架,應(yīng)在管外包橡膠墊圈。5) 暗裝或埋地的排水管道,在隱蔽前必須做灌水試驗(yàn),其灌水高度應(yīng)不低于底層地面高度。6) 雨水管道不得與生活污水管道相連接。7) 雨水管道安裝后,應(yīng)做灌水試驗(yàn),灌水高度必須到每根立管最上部的雨水漏斗。
(3)施工過(guò)程中的質(zhì)量通病的防治。預(yù)制好的管段彎曲或斷裂。原因是直管堆放未墊實(shí)或曝曬所致;接口處外觀不清潔,美觀。粘接后外溢粘接劑應(yīng)及時(shí)除掉;粘接口漏水。原因是粘接劑涂刷不均勻,或粘接處未處理干凈所致;地漏安裝過(guò)高過(guò)低,影響使用。原因是地平線未找準(zhǔn);立管穿樓板處滲水,原因是立管穿樓板處沒(méi)有做防水處理,在穿樓板的地方應(yīng)該做好防水處理。
3結(jié)語(yǔ)
總之,建筑給排水工程的監(jiān)理工程師要嚴(yán)格按照施工單位和業(yè)主的要求,在給排水施工過(guò)程在施工圖、施工工序、設(shè)計(jì)要求、驗(yàn)收規(guī)定、施工規(guī)范及其它有關(guān)安裝規(guī)范的施工過(guò)程中嚴(yán)格把關(guān),才能避免工程施工中的質(zhì)量問(wèn)題,進(jìn)一步完善和提高給排水工程質(zhì)量。
參考文獻(xiàn):
[1]魏明超.淺談給排水工程監(jiān)理工作中的幾個(gè)問(wèn)題[B].山西建筑.2007 年,第 33 卷第 14 期.
[2]何錦棠.給排水工程施工階段監(jiān)理的分析[J].科技創(chuàng)新導(dǎo)報(bào),2009.
【關(guān)鍵詞】監(jiān)理;給排水施工;問(wèn)題;質(zhì)量研究
1.給排水施工中存在的主要問(wèn)題
(1)不重視工程預(yù)留、預(yù)埋,給后期安裝造成了不必要的麻煩。在工程主體結(jié)構(gòu)施工階段,給排水專業(yè)工作主要是預(yù)留、預(yù)埋,施工單位對(duì)此普遍不夠重視,有的工地配備1個(gè)給排水專業(yè)施工人員,有的工地則由土建施工人員代勞,預(yù)留定位不準(zhǔn)確,導(dǎo)致后期安裝定位偏差過(guò)大,進(jìn)行樓板打洞,極易打斷鋼筋,影響結(jié)構(gòu)安全,或預(yù)埋套管漏埋,給后期工程質(zhì)量帶來(lái)隱患。
(2)安裝過(guò)程隨意性大。對(duì)圖紙看的不細(xì),不能很好的理解設(shè)計(jì)意圖,對(duì)管道標(biāo)高、位置不能嚴(yán)格按照?qǐng)D紙和規(guī)范要求安裝,尺寸偏差較大,影響衛(wèi)生間整體布局。
(3)質(zhì)量過(guò)程控制不嚴(yán)格。存在以通水代替沖洗、試壓現(xiàn)象。部分施工單位以工期緊為理由,室內(nèi)給水管道安裝后不對(duì)管道進(jìn)行沖洗、試壓。而是直接將外網(wǎng)接入,利用外網(wǎng)的水進(jìn)行沖洗,導(dǎo)致部分龍頭、小便器沖洗閥等堵塞。不按照規(guī)范要求的工作壓力的1.5倍進(jìn)行試壓,認(rèn)為在工作壓力下不漏水即可,給以后的使用帶來(lái)了隱患。
(4)未做好成品保護(hù)。由于安裝過(guò)程和裝飾裝修過(guò)程存在交叉作業(yè),安裝完畢的管道經(jīng)常因未做好成品保護(hù)而導(dǎo)致排水管道掉入雜物造成堵塞?;蛘咴趪姖{時(shí)管道未保護(hù)導(dǎo)致污染,施工人員不注意將安裝完畢的管道碰壞等。
2.建筑給排水施工中監(jiān)理的控制重點(diǎn)
(1)把好施工組織設(shè)計(jì)審核關(guān)。施工組織設(shè)計(jì)是施工單位施工的指導(dǎo)和依據(jù),施工組織設(shè)計(jì)應(yīng)根據(jù)工程特點(diǎn)、給排水系統(tǒng)形式、施工組織等進(jìn)行編制,應(yīng)具有針對(duì)性、實(shí)用性,避免大眾化、通用性。監(jiān)理單位應(yīng)對(duì)施工組合設(shè)計(jì)進(jìn)行仔細(xì)審核,對(duì)施工中易出現(xiàn)的問(wèn)題做好預(yù)想預(yù)防。
(2)把好進(jìn)場(chǎng)材料驗(yàn)收關(guān)。在工程監(jiān)理過(guò)程中發(fā)現(xiàn),給排水材料魚龍混雜、良莠不齊,監(jiān)理人員應(yīng)對(duì)進(jìn)場(chǎng)材料進(jìn)行驗(yàn)收,做到進(jìn)場(chǎng)材料質(zhì)量合格,符合設(shè)計(jì)要求和合同要求。還應(yīng)對(duì)進(jìn)場(chǎng)的不合格材料能夠分辨與識(shí)別,并要求施工單位清出場(chǎng),嚴(yán)禁用于工程。
(3)把好關(guān)鍵工序質(zhì)量驗(yàn)收關(guān)。對(duì)排水系統(tǒng)的灌水、通水、通球試驗(yàn)、給水系統(tǒng)的試壓、沖洗、通水等關(guān)系安全與功能的檢測(cè)試驗(yàn)按照規(guī)范要求進(jìn)行檢驗(yàn),做好試驗(yàn)記錄,做到不留隱患。對(duì)檢驗(yàn)批、分項(xiàng)、分部工程的驗(yàn)收嚴(yán)格把關(guān),主控項(xiàng)目應(yīng)100%合格,一般項(xiàng)目應(yīng)在誤差允許范圍內(nèi)。
3.建筑給排水施工監(jiān)理的具體措施
3.1施工準(zhǔn)備階段
工程施工前期監(jiān)理人員主要熟悉圖紙,了解設(shè)計(jì)意圖。主要包括了解設(shè)計(jì)要求的管材、管件、連接方式、潔具型式,與外線的連接等。找出圖紙中設(shè)計(jì)有矛盾或安裝過(guò)程中難以實(shí)現(xiàn)的地方,以及與其他專業(yè)位置有沖突的地方,在圖紙會(huì)審時(shí)將問(wèn)題一并提出。請(qǐng)?jiān)O(shè)計(jì)單位對(duì)這些圖紙中存在的問(wèn)題進(jìn)行解決。審核施工單位施工組織設(shè)計(jì)時(shí)主要看施工組織設(shè)計(jì)的審批程序是否合理,施工單位的專業(yè)施工進(jìn)度安排是否合理,是否在組織設(shè)計(jì)中對(duì)專業(yè)施工人員的施工進(jìn)度計(jì)劃進(jìn)行了詳細(xì)安排,施工工序是否合理,關(guān)鍵環(huán)節(jié)的質(zhì)量控制措施是否制定,是否具有針對(duì)性,能否實(shí)現(xiàn);安全文明施工及成品保護(hù)措施是否到位等。編制給排水專業(yè)監(jiān)理細(xì)則,在工程開工之前,應(yīng)依據(jù)設(shè)計(jì)圖紙、施工質(zhì)量驗(yàn)收規(guī)范等編制出符合工程實(shí)際的監(jiān)理細(xì)則,用以指導(dǎo)工程監(jiān)理工作。
3.2土建主體結(jié)構(gòu)施工階段
工程主體結(jié)構(gòu)施工階段的主要工作是預(yù)留、預(yù)埋。施工單位需派專門的給排水施工人員跟隨土建工程進(jìn)度安排給排水工程的預(yù)留、預(yù)埋工作。在基礎(chǔ)施工時(shí),需要對(duì)給排水管道穿基礎(chǔ)的預(yù)留洞進(jìn)行預(yù)留,預(yù)留過(guò)程中要求找準(zhǔn)洞的位置、標(biāo)高,大小應(yīng)符合設(shè)計(jì)要求;在樓面板施工時(shí)給排水施工人員應(yīng)在混凝土澆筑前對(duì)給排水的預(yù)留洞進(jìn)行留置,要求定位必須準(zhǔn)確、固定牢固,上下層位置一致,距墻的距離不超過(guò)允許偏差,預(yù)留洞的大小圖紙中一般不給出,通常按照規(guī)范和施工工藝標(biāo)準(zhǔn)進(jìn)行,DN100的管道預(yù)留洞為200mm×200mm,DN50的管道預(yù)留洞為150mm×150mm,衛(wèi)生間給水管道暗裝時(shí),在衛(wèi)生間隔墻砌筑時(shí)對(duì)預(yù)埋管道的凹槽進(jìn)行預(yù)留,凹槽的標(biāo)高、位置應(yīng)能滿足設(shè)計(jì)要求,深度應(yīng)為管道外徑加2cm,凹槽內(nèi)應(yīng)光滑,不應(yīng)有尖銳的棱角,防止損傷管道。
3.3裝飾裝修階段
(1)埋地管道的質(zhì)量監(jiān)理。埋地的給水管道基礎(chǔ)應(yīng)平整,在隱蔽之前應(yīng)進(jìn)行試壓,試驗(yàn)壓力應(yīng)按照設(shè)計(jì)要求或不小于0.6MPa,要求管道不滲不漏試壓合格后有防腐要求的管道應(yīng)進(jìn)行防腐,防腐驗(yàn)收合格后方可進(jìn)行回填。埋地的排水管道基礎(chǔ)應(yīng)夯實(shí),平整并按照排水管道的坡度坡向室外,管道安裝后進(jìn)行可靠固定,隱蔽前進(jìn)行灌水試驗(yàn),灌水高度不小于建筑物地面高度,滿水15min后液面下降,再灌滿5min后液面不降為合格。合格后鑄鐵管還應(yīng)刷兩遍瀝青漆進(jìn)行防腐。埋地管道回填時(shí)應(yīng)人工回填,每層回填30cm進(jìn)行人工夯實(shí),嚴(yán)禁機(jī)械夯實(shí),防止安裝好的管道被壓壞。
(2)地面以上給水管道的質(zhì)量監(jiān)理。給水管道的驗(yàn)收主要看給水管道的管材、閥門型號(hào)是否符合設(shè)計(jì)要求,標(biāo)高、位置符合設(shè)計(jì)要求,應(yīng)做到橫平豎直,監(jiān)理人員應(yīng)依據(jù)圖紙逐一檢查,閥門應(yīng)啟閉靈活;管道安裝穿樓板、穿墻應(yīng)設(shè)置套管,套管高度是否滿足規(guī)范要求,并用不燃柔性材料進(jìn)行了封堵,應(yīng)按照規(guī)范要求設(shè)置管卡,間距符合要求,安裝牢固;對(duì)給水系統(tǒng)進(jìn)行試壓,管材為金屬管時(shí)要求試驗(yàn)壓力不小于0.6MPa,試驗(yàn)15min后降至工作壓力檢查,管道應(yīng)不滲不漏,在監(jiān)理過(guò)程中發(fā)現(xiàn)給水管道的易漏水的地方主要是閥門的閥桿、活節(jié)以及和潔具的連接處,這些部位應(yīng)重點(diǎn)檢查。衛(wèi)生間暗裝管道一般為PPR管,應(yīng)注意檢查冷、熱水管安裝位置為上熱下冷、左熱右冷、冷熱水管材不能用混、試壓應(yīng)為3h,并進(jìn)行通水試驗(yàn),看管道是否堵塞。
(3)地面以上排水管道的質(zhì)量監(jiān)理。地面以上排水管道安裝主要管道坡度應(yīng)符合設(shè)計(jì)要求,嚴(yán)禁無(wú)坡或倒坡;控制管件的使用應(yīng)符合設(shè)計(jì)和規(guī)范要求,不能使用正三通,不能使用曲率半徑小于4倍管徑的90°彎頭;排水立管檢查口位置,伸縮節(jié)位置,清掃口位置均應(yīng)滿足設(shè)計(jì)和規(guī)范要求;還應(yīng)檢查排水管道潔具預(yù)留管口的位置應(yīng)能滿足潔具安裝要求,應(yīng)結(jié)合潔具的品牌、型號(hào)進(jìn)行確定,防止因潔具型號(hào)不確定導(dǎo)致后期排水管道安裝返工。安裝中采用的地漏是否符合設(shè)計(jì)要求,嚴(yán)禁采用鐘罩式或扣碗式地漏,但在本地仍應(yīng)用較多。吊頂內(nèi)隱蔽的管道還應(yīng)做灌水試驗(yàn),在實(shí)際監(jiān)理中發(fā)現(xiàn)由于排水立管的水較難進(jìn)行封堵,通常以通水試驗(yàn)代替灌水試驗(yàn)。安裝完成后還應(yīng)進(jìn)行通球試驗(yàn),檢查管道是否堵塞。
3.4竣工驗(yàn)收階段
工程竣工驗(yàn)收時(shí)不但對(duì)給排水安裝的功能與安全檢測(cè)資料進(jìn)行檢查,同時(shí)進(jìn)行實(shí)地檢驗(yàn),給水龍頭應(yīng)通水順暢,管道應(yīng)不滲不漏;地漏、大便器等排水通暢;對(duì)外觀質(zhì)量進(jìn)行檢查,檢查管道刷漆質(zhì)量、管道走向、閥門、支架安裝位置,潔具安裝位置等。驗(yàn)收合格后方可簽署質(zhì)量評(píng)估報(bào)告。
4.結(jié)束語(yǔ)
給排水專業(yè)監(jiān)理人員應(yīng)以規(guī)范、設(shè)計(jì)為依據(jù),針對(duì)工程中易出現(xiàn)的問(wèn)題,審核施工組織設(shè)計(jì),做到事前控制,對(duì)安裝過(guò)程進(jìn)行檢查、巡視,功能檢測(cè)試驗(yàn)進(jìn)行檢查驗(yàn)收,及時(shí)發(fā)現(xiàn)問(wèn)題,做到事中控制,對(duì)存在的問(wèn)題提出整改措施,做到事后控制。把好工程質(zhì)量驗(yàn)收關(guān),督促施工單位規(guī)范施工,確保工程質(zhì)量。
【參考文獻(xiàn)】
[1]GB50242-202,建筑給水排水及采暖工程施工質(zhì)量驗(yàn)收規(guī)范[S].
[2]劉淑霞.監(jiān)理工程師應(yīng)加強(qiáng)建筑給排水安裝工程中的全過(guò)程質(zhì)量管理[A].科學(xué)發(fā)展—七省市第九屆建筑市場(chǎng)與招標(biāo)投標(biāo)優(yōu)秀論文集[C].天津:天津科技翻譯出版公司,2009:757-761.
關(guān)鍵詞:市政;雨污水;問(wèn)題;措施
中圖分類號(hào):TU99文獻(xiàn)標(biāo)識(shí)碼: A
1、確保市政雨污水的管道施工質(zhì)量的重要性
市政排水管道工程是城市建設(shè)的基礎(chǔ)工程之一。由于工程施工質(zhì)量問(wèn)題,工程粗糙,容易造成管道斷裂泄露、排水不暢、水倒流和路面發(fā)生沉陷或變形,導(dǎo)致市政排水管道工程質(zhì)量無(wú)法得到保證。市政排水管道工程質(zhì)量的好壞與人民生活密切相關(guān),其使用功能是否完善,直接涉及千家萬(wàn)戶的利益。因此確保排水管道工程施工質(zhì)量至關(guān)重要。
2、市政雨污水管道施工存在的問(wèn)題
2.1、員工的質(zhì)量意識(shí)淡薄
市政雨污水管道的施工不同于其他的建筑工程,它有自己一定的特殊性,而現(xiàn)階段,我國(guó)很多的市政與污水管道的建設(shè)現(xiàn)狀來(lái)看,他們很多都為了利益的最大化而盲目的追求工期卻忽視了工程的質(zhì)量。主要表現(xiàn)在:在市政雨污水管道的施工過(guò)程中,各個(gè)環(huán)節(jié)以及相關(guān)工程段的責(zé)任主體不能很好地熟悉相關(guān)的標(biāo)準(zhǔn),最終造成工程質(zhì)量的低下,比如在具體的工作中出現(xiàn)一些雨污水的管道建設(shè)的各段施工主體經(jīng)常出現(xiàn)后補(bǔ)資料、資料不真實(shí)等的情況,影響著工程的質(zhì)量。
2.2、管道施工路線不合理
在市政雨污水管道的建設(shè)施工的過(guò)程中,有很多的管道施工單位為了節(jié)省工程的成本,往往對(duì)于所選擇的管道線路都不符合當(dāng)?shù)氐膶?shí)際情況,這就會(huì)造成一些市政管道工程的質(zhì)量出現(xiàn)一定的問(wèn)題。
2.3、排水管道配件老化
在具體的市政管道的建設(shè)、使用過(guò)程中,由于排水管道的使用時(shí)間過(guò)長(zhǎng),就造成管道的生銹老化、閥門質(zhì)量出現(xiàn)問(wèn)題等等,這就造成了一定水資源的浪費(fèi)。同時(shí)還包括有由于在市政的建設(shè)過(guò)程中,由于排水配件閥的壓力過(guò)大,造成超壓外流,最終影響到工程的質(zhì)量。
2.4、施工管理不規(guī)范
現(xiàn)階段,我國(guó)相當(dāng)一部分的市政雨污水管道在其施工的過(guò)程中,都沒(méi)有相關(guān)的施工許可證以及相關(guān)的工程質(zhì)量監(jiān)督手續(xù)等等,在具體的工作中只是簡(jiǎn)單的在當(dāng)上級(jí)主管部門要檢查的時(shí)候進(jìn)行臨時(shí)的補(bǔ)辦手續(xù),這樣就對(duì)工程質(zhì)量的提高極為不利。
2.5、市場(chǎng)管理不規(guī)范
市政工程的業(yè)主很多都來(lái)自于政府或者主管部門,這樣由于有些單位依據(jù)自身的權(quán)利不按照政府規(guī)定辦事,忽視工程監(jiān)理制、合同管理制等制度,甚至有的工程還沒(méi)有簽訂正式施工合同就已經(jīng)開工很久了,違背了先合同后開工的原則,影響工程的質(zhì)量。
3、市政雨污水的管道施工的要點(diǎn)
3.1、施工前
3.1.1、認(rèn)真審核設(shè)計(jì)圖紙
工程施工前,首先要對(duì)相關(guān)的工程設(shè)計(jì)文件以及相關(guān)的施工圖紙等進(jìn)行全面的會(huì)審。主要檢查是否符合具體的施工實(shí)際、設(shè)計(jì)的深度是否滿足施工的要求,要努力盡量的避免由于工程設(shè)計(jì)上的問(wèn)題給工程的施工帶來(lái)的不良影響。
3.1.2、開工申請(qǐng)及監(jiān)理細(xì)則
對(duì)于市政雨污水管道的具體施工之前,要特別的注意,相關(guān)的工作人員要根據(jù)排工程的實(shí)際特點(diǎn)以及相關(guān)的設(shè)計(jì)要求來(lái)做充分的開工申請(qǐng)工作,與此同時(shí)要根據(jù)相關(guān)的法律法規(guī)并制定相應(yīng)的工程質(zhì)量監(jiān)理細(xì)則。
3.1.3、設(shè)立安全警示標(biāo)志
在街道上施工,挖土前必須在溝槽兩端設(shè)立安全設(shè)施,如路障及危險(xiǎn)旗之類的警告標(biāo)志。挖槽前還要了解該段的土質(zhì)、水文以及地下構(gòu)造物的位置,靠近建筑物挖槽時(shí),應(yīng)事先做好地面清障工作及制定安全防護(hù)措施。
3.2、施工中
3.2.1、溝槽開挖與支護(hù)
在市政雨污水管道的建設(shè)過(guò)程中,在開挖前要清楚地下既有的管道,把合理的建設(shè)方案送交到相關(guān)管理單位進(jìn)行確認(rèn),以此保證工程的順利進(jìn)行。還要特別的注意,當(dāng)?shù)叵滤惠^高或者在雨季進(jìn)行施工的時(shí)候,要求采取一定的排水措施,保證水位低于工作面2m,防止溝槽內(nèi)長(zhǎng)時(shí)間的積水,造成浮管視為現(xiàn)象。
3.2.2、塑料埋地排水管道的施工技術(shù)
敷設(shè)的條件和質(zhì)量對(duì)于其是否能夠安全工作起到?jīng)Q定性的作用。所以對(duì)設(shè)計(jì)而言,應(yīng)在設(shè)計(jì)中強(qiáng)調(diào)敷設(shè)的重要性,而對(duì)施工方來(lái)說(shuō),應(yīng)重視敷設(shè)的重要性,改變以往敷設(shè)混凝土管的粗放野蠻施工方法,保證塑料埋地排水管的優(yōu)異性能,促進(jìn)其順利的推廣應(yīng)用。
3.2.3、管道閉水試驗(yàn)
在工作中采取閉水試驗(yàn),這是檢查管道的施工質(zhì)量的重要措施,要注意在閉水試驗(yàn)前須做好準(zhǔn)備的工作,對(duì)閉水試驗(yàn)的管段進(jìn)行每根管材進(jìn)行了嚴(yán)格仔細(xì)的檢查,對(duì)有裂縫進(jìn)行必要的修補(bǔ),經(jīng)過(guò)嚴(yán)格的閉水試驗(yàn)之后,對(duì)閉水不合格的管段進(jìn)行補(bǔ)救或返工,待到閉水試驗(yàn)完成合格后才能進(jìn)行土方回填的工作。
3.2.4、溝槽回填施工管理
在管道的回填方面,回填的方式較多,人工回填方法是最普遍的,在施工作業(yè)之前,需要進(jìn)行相關(guān)的檢查工作,在檢查無(wú)誤后,便可進(jìn)行澆蓋工作。并且在澆蓋的過(guò)程中為了確保澆蓋的完整性,以保證回填施工的質(zhì)量,對(duì)溝槽的回填作業(yè)中,溝槽內(nèi)要確保無(wú)雜物,槽內(nèi)不能有積水。在回填時(shí),基底排水方向應(yīng)該設(shè)置成從高到低,并在管道的兩側(cè)進(jìn)行填土,兩側(cè)的高度差應(yīng)該超過(guò)30厘米。
4、市政雨污水的管道施工問(wèn)題的預(yù)防措施
4.1、加強(qiáng)對(duì)施工人員的管理
首先是在選擇施工人員時(shí),要注意選擇具有相關(guān)的施工經(jīng)驗(yàn),并且具有很好的專業(yè)素質(zhì)的施工隊(duì)伍進(jìn)行施工。其次是要經(jīng)常對(duì)施工人員進(jìn)行技術(shù)、質(zhì)量與安全知識(shí)的教育和培訓(xùn),從而幫助施工人員從思想上和技術(shù)上逐步提高專業(yè)的施工技術(shù)和安全質(zhì)量的意識(shí)。再次是嚴(yán)格要求施工管理人員在施工之前,認(rèn)真做好技術(shù)交底的相關(guān)工作,對(duì)于工程施工過(guò)程中有可能出現(xiàn)的某些質(zhì)量問(wèn)題,應(yīng)該提前提出相關(guān)的質(zhì)量控制對(duì)策。
4.2、加強(qiáng)材料、設(shè)備的管理
建筑材料的質(zhì)量直接影響著工程的質(zhì)量,所以在工作中必須嚴(yán)格控制好材料、設(shè)備質(zhì)量。對(duì)材料、設(shè)備進(jìn)行統(tǒng)一的管理和采購(gòu),確保施工中使用的管材是經(jīng)過(guò)專業(yè)檢驗(yàn)合格,而且有相應(yīng)的檢驗(yàn)合格報(bào)告的產(chǎn)品。在進(jìn)場(chǎng)時(shí)要檢查三證是否齊全,證件、手續(xù)不齊全的材料設(shè)備也不應(yīng)采用,以免留下質(zhì)量隱患。尤其是對(duì)管材的選用和檢查的質(zhì)量控制預(yù)防是整個(gè)施工質(zhì)量的關(guān)鍵。在給排水工程中,選材的質(zhì)量合格為給排水管道打好堅(jiān)實(shí)的基礎(chǔ),避免了由管道質(zhì)量而影響給排水管道的施工質(zhì)量。
4.3、做好設(shè)計(jì)圖紙的審核
工程施工前,要認(rèn)真做好設(shè)計(jì)文件、施工圖紙等的會(huì)審和核查工作。審核工作具體包括檢查設(shè)計(jì)深度是否滿足施工要求,檢查設(shè)計(jì)圖紙是否與施工現(xiàn)場(chǎng)實(shí)際相符,檢查給排水管道在平面位置及斷面標(biāo)高上是否同結(jié)構(gòu),是否與暖通空調(diào)、電力、通信等其他管線存在沖突等內(nèi)容。
綜上所述,在城建快速發(fā)展的今天,為了在日趨激烈的商業(yè)競(jìng)爭(zhēng)中能夠占據(jù)優(yōu)勢(shì)地位,相關(guān)施工企業(yè)單位就要嚴(yán)格按照相關(guān)施工程序進(jìn)行施工,加強(qiáng)每個(gè)環(huán)節(jié)的施工質(zhì)量控制,有效的防止工程事故的發(fā)生,最終達(dá)到提升市政排水管道工程的施工質(zhì)量,從而促進(jìn)我國(guó)施工企業(yè)的發(fā)展。
參考文獻(xiàn)
[1]羅曄,張建軍.市政雨污水管線的施工與質(zhì)量管理淺析[J].中華民居(下旬刊),2013,06:128-129.
[2]李來(lái)明.綜述市政雨污水的管道施工及防治[J].山西建筑,2013,33:119-120.
【關(guān)鍵詞】工程監(jiān)理;施工階段;質(zhì)量控制;研究
在工程建設(shè)階段,施工階段并不是單一的,通過(guò)其它階段對(duì)施工階段的配合,從而保證施工質(zhì)量。而工程建設(shè)監(jiān)理就是接受建設(shè)單位的委托,代表建設(shè)單位對(duì)工程進(jìn)行全方位的跟蹤監(jiān)督,確保工程質(zhì)量??刂坪酶鱾€(gè)施工階段的工程質(zhì)量是施工監(jiān)理的任務(wù),也是目的,也是整個(gè)工程建設(shè)的根本。通過(guò)工程監(jiān)理對(duì)整個(gè)施工階段的質(zhì)量控制,從而保證工程質(zhì)量。
1 工程監(jiān)理在施工階段中的目的與任務(wù)
任何工程建設(shè)都不能缺少工程監(jiān)理,是因?yàn)楣こ瘫O(jiān)理通過(guò)自己的專業(yè)知識(shí)和責(zé)任心,盡心盡力做好自己的本職工作。只有監(jiān)理部門采取積極有效的措施,完成業(yè)主交給他的任務(wù),保證施工質(zhì)量,監(jiān)理部門才能存在,工程監(jiān)理在施工階段監(jiān)理的最主要的任務(wù)有以下三點(diǎn):1.施工階段的質(zhì)量控制,包括對(duì)工程重點(diǎn)的監(jiān)理、對(duì)隱匿工程的檢查和辦理簽證,對(duì)施工測(cè)量和放樣的檢查;對(duì)分部分項(xiàng)工程的評(píng)定,對(duì)有質(zhì)量問(wèn)題的工程及時(shí)糾正,并做相應(yīng)的記錄;對(duì)材料和構(gòu)件進(jìn)行質(zhì)量測(cè)驗(yàn),并查看相應(yīng)的報(bào)告單,對(duì)不符合要求的材料和設(shè)備禁止進(jìn)入場(chǎng)地使用;嚴(yán)格監(jiān)督施工合同;適時(shí)地對(duì)工程的自檢工作給予評(píng)價(jià);對(duì)各種檢測(cè)設(shè)備進(jìn)行檢查;按規(guī)定檢查各類土木和混凝土;對(duì)嚴(yán)重事故應(yīng)及時(shí)報(bào)告業(yè)主。2.施工階段的進(jìn)度控制,包括監(jiān)督施工單位嚴(yán)格按照施工合同規(guī)定的工期組織施工;進(jìn)行施工進(jìn)度的動(dòng)態(tài)控制;一定要做好的相應(yīng)的進(jìn)度臺(tái)帳,以便于定期的向業(yè)主報(bào)告工程進(jìn)度情況國(guó)。3.施工階段的投資控制,監(jiān)理在整個(gè)監(jiān)理過(guò)程中還要進(jìn)行投資控制。包括工程數(shù)量的核對(duì),對(duì)月度和季度計(jì)量表的審查,為便于與施工單位進(jìn)行核對(duì),應(yīng)建立相應(yīng)原計(jì)量臺(tái)帳。所以說(shuō),工程監(jiān)理控制著整個(gè)工程的質(zhì)量,在施工階段中有非常重要的作用,可以說(shuō),一個(gè)工程建設(shè)的質(zhì)量如何,全在監(jiān)理工作人員,當(dāng)然一個(gè)監(jiān)理的態(tài)度也很重要。態(tài)度決定工程質(zhì)量。所以說(shuō),工程監(jiān)理對(duì)建設(shè)工程中不可缺少??傊O(jiān)理部門在明確監(jiān)理目標(biāo)值的基礎(chǔ)上,制定和選出科學(xué)而合理的控制方法措施,從而保證施工階段中各項(xiàng)目的控制目的。
2 施工階段質(zhì)量控制中工程監(jiān)理的原則及程序
把質(zhì)量放在第一位是工程監(jiān)理的工作原則,在整個(gè)監(jiān)理過(guò)程中一定要把質(zhì)量第一貫穿于始終。在整個(gè)施工中,禁不合格的單位進(jìn)行施工,禁止不合格的構(gòu)件和材料進(jìn)入場(chǎng)地。
在施工階段,工程監(jiān)理的監(jiān)理過(guò)程是整個(gè)施工過(guò)程,對(duì)施工過(guò)程中的每一道工序,每一個(gè)細(xì)節(jié)都要監(jiān)理到位,才能保證施工質(zhì)量。從工程開工到結(jié)束驗(yàn)收的全過(guò)程,工程監(jiān)理對(duì)各子單位工程的所有材料及設(shè)備都要嚴(yán)格把關(guān)。
承包單位在做好所有開工前的準(zhǔn)備后,同時(shí)提交相關(guān)的實(shí)驗(yàn)證明書及報(bào)告材不料,就可以開工了。監(jiān)理要對(duì)承包單位開工前做的這一切進(jìn)行仔細(xì)檢查。當(dāng)檢查所有的材料及報(bào)告都沒(méi)有問(wèn)題的前提下,才可以簽發(fā)開工命令并報(bào)建設(shè)單位。在簽發(fā)開工令后,監(jiān)理部門負(fù)責(zé)對(duì)整個(gè)施工過(guò)程進(jìn)行全面巡視和檢查。尤其對(duì)于一些隱蔽工程或者工程的重點(diǎn)部位要更加嚴(yán)查,必要時(shí)要安排旁站監(jiān)理。對(duì)于其它單位送來(lái)的報(bào)驗(yàn)單,各相關(guān)檢驗(yàn)結(jié)果應(yīng)仔細(xì)檢查,嚴(yán)格把關(guān)。專業(yè)監(jiān)理工程師要嚴(yán)格審核符合要求后才能予以簽認(rèn)。
當(dāng)發(fā)現(xiàn)施工過(guò)程中存在質(zhì)量隱患時(shí),應(yīng)下令讓承包單位認(rèn)真整改,并仔細(xì)檢查整改結(jié)果,結(jié)果合格后才能進(jìn)行下面的工作。對(duì)于隱蔽工程,監(jiān)理工程師一定要更加小心檢查,發(fā)現(xiàn)問(wèn)題,不能放過(guò)任何一條可疑問(wèn)題。當(dāng)然,對(duì)于需要返工的工程,承包單位必須認(rèn)真重整,并報(bào)送相關(guān)的報(bào)告,經(jīng)設(shè)計(jì)單位的認(rèn)可后,方可通過(guò)。對(duì)于質(zhì)量事故處理的全過(guò)程,監(jiān)理應(yīng)保證對(duì)全過(guò)程進(jìn)行全面跟蹤,并對(duì)結(jié)果進(jìn)行查驗(yàn)。另外,各子項(xiàng)目工程在結(jié)束工程后,必須填報(bào)分項(xiàng)工程報(bào)檢單,并報(bào)送監(jiān)理機(jī)構(gòu)驗(yàn)收,監(jiān)理工程機(jī)構(gòu)組織的相關(guān)工作人員進(jìn)行現(xiàn)場(chǎng)的質(zhì)量檢查,并對(duì)相關(guān)資料進(jìn)行核查。總之,在施工階段的各個(gè)子單位工程審查及完工后的驗(yàn)收結(jié)果中。工程監(jiān)理通過(guò)親自審查、核對(duì)相關(guān)數(shù)據(jù)資料,符合要求即可驗(yàn)收簽認(rèn),一旦發(fā)現(xiàn)任何質(zhì)量不達(dá)標(biāo)立即通知相關(guān)單位整改,直至整改結(jié)果符合要求后才通過(guò)。
3 施工階段中工程監(jiān)理的控制內(nèi)容及方法
在整個(gè)工程項(xiàng)目的過(guò)程中,施工階段是方面,即是對(duì)原材料及施工設(shè)備的質(zhì)量控制到工程竣工質(zhì)量驗(yàn)收的系統(tǒng)質(zhì)量控制過(guò)程。在這個(gè)過(guò)程中,監(jiān)理的主要內(nèi)容分為以下三個(gè)階段:
第一,質(zhì)量控制是施工準(zhǔn)備階段的控制。1.施工技術(shù)資料的質(zhì)量控制。在工程項(xiàng)目開工前,工程監(jiān)理應(yīng)負(fù)責(zé)審查對(duì)各項(xiàng)書面資料,并檢查主要的施工設(shè)備。對(duì)于不完整的資料應(yīng)責(zé)令提供完整的資料,對(duì)于不合格的施工設(shè)備應(yīng)返回讓其提供合格的施工設(shè)備,并提供設(shè)備的技術(shù)性能報(bào)告。②施工測(cè)量的質(zhì)量控制。對(duì)于專職的測(cè)量人員,工程監(jiān)理機(jī)構(gòu)應(yīng)對(duì)其崗位證書和測(cè)量設(shè)備檢定證書進(jìn)行仔細(xì)審核;并對(duì)其專業(yè)知識(shí)進(jìn)行測(cè)試。③在工程項(xiàng)目開工前,進(jìn)行施工技術(shù)方案的質(zhì)量控制,工程監(jiān)理機(jī)構(gòu)應(yīng)對(duì)承包單位報(bào)送的施工組織設(shè)計(jì),提出相關(guān)的審查意見,經(jīng)相關(guān)機(jī)構(gòu)簽認(rèn)后報(bào)建設(shè)單位。
第二,施工過(guò)程階段的質(zhì)量控制。首先,工程監(jiān)理機(jī)構(gòu)要對(duì)施工過(guò)程中要用到的原材料進(jìn)行試驗(yàn)檢查其質(zhì)量,并且特別是對(duì)新材料應(yīng)用的檢測(cè),確保工程質(zhì)量。其次,對(duì)于承包單位提供的計(jì)量設(shè)備,工程監(jiān)理應(yīng)該進(jìn)行定期檢查以便宜保證設(shè)備在工程中的正常使用。在施工的過(guò)程中,對(duì)于修改施工圖紙的問(wèn)題,應(yīng)根據(jù)實(shí)際情況及相關(guān)資料經(jīng)專業(yè)監(jiān)理工程師審查并經(jīng)項(xiàng)目監(jiān)理機(jī)構(gòu)后方可變動(dòng),變動(dòng)后的圖紙一定要經(jīng)過(guò)工程師審查后交總由總監(jiān)進(jìn)行簽字確認(rèn)后,方可實(shí)施。最后,當(dāng)遇到未經(jīng)同意而變更施工方案,和對(duì)未經(jīng)審核及審核不達(dá)標(biāo)的材料使用,以及在施工中前道工序未經(jīng)檢驗(yàn)或者是驗(yàn)收不合格而進(jìn)行下道工序的等出現(xiàn)其中一個(gè)現(xiàn)象的就應(yīng)及時(shí)下達(dá)工程暫停令。
第三,竣工驗(yàn)收階段的質(zhì)量控制。對(duì)于已經(jīng)結(jié)束的工程項(xiàng)目,工程監(jiān)理機(jī)構(gòu)應(yīng)對(duì)其進(jìn)行檢查驗(yàn)收,審查合格后予以簽認(rèn)。在項(xiàng)目驗(yàn)收階段如果發(fā)現(xiàn)質(zhì)量問(wèn)題,應(yīng)先分析原因,然后提出合理化的意見和整改措施,并且要讓責(zé)任人承擔(dān)相關(guān)的責(zé)任,對(duì)于損失嚴(yán)重的應(yīng)承擔(dān)相應(yīng)的法律責(zé)任。至到整改結(jié)果合格后,方可通過(guò)。為了確保工程項(xiàng)目的高質(zhì)量水平,必須要嚴(yán)格控制驗(yàn)收質(zhì)量,也就是說(shuō)在監(jiān)理工作人員在已完成的工作基礎(chǔ)上加以完善。
4 結(jié)束語(yǔ)
綜上所述,任何工程都要把質(zhì)量問(wèn)題放在重要位置,一旦工程質(zhì)量出現(xiàn)問(wèn)題,那么不僅僅是投資損失,更主要的是它可能會(huì)人們帶來(lái)更大的危害。所以說(shuō),在整個(gè)施工階段過(guò)程中。監(jiān)理機(jī)構(gòu)對(duì)施工質(zhì)量的控制不能只停留在監(jiān)督與檢查的要求上,工程監(jiān)理部門應(yīng)該根據(jù)工程項(xiàng)目的內(nèi)容及要求特點(diǎn)等方面,并結(jié)合以前的監(jiān)理經(jīng)驗(yàn)制定出系統(tǒng)而又科學(xué)合理的監(jiān)理規(guī)程和實(shí)施細(xì)則及控制程序,這樣才能更有效的保證工程監(jiān)理在質(zhì)量控制上更加規(guī)范化和有序化。為了提高我國(guó)建設(shè)工程的質(zhì)量,必須要加強(qiáng)施工過(guò)程中的質(zhì)量控制。這是最終達(dá)到工程監(jiān)理在施工階段過(guò)程中質(zhì)量控制的目的。
參考文獻(xiàn)
[1]谷金明.吳天驕.建設(shè)工程監(jiān)理施工階段的質(zhì)量控制方法研究[J].黑龍江科技信息,2012(4)
[2]曹興麗.淺談給排水工程施工監(jiān)理質(zhì)量控制[J].城市建設(shè)理論研究,2011(11)
[3]陳海.淺談施工階段的工程質(zhì)量監(jiān)理[J].當(dāng)代生態(tài)農(nóng)業(yè),2011(7)
關(guān)鍵詞:建筑工程;檔案管理;問(wèn)題;思考
Abstract: the file management is building project construction process an important link in the engineering quality and the management level is the real response, this paper expounds the construction engineering archives material content and the main problems existing in the foundation, the union a renovation project example, during the project construction in the file management main work are introduced, have certain reference significance.
Keywords: building engineering; File management; Problem; thinking
中圖分類號(hào): G271文獻(xiàn)標(biāo)識(shí)碼:A 文章編號(hào):
所謂檔案,中華人民共和國(guó)檔案行業(yè)標(biāo)準(zhǔn)《檔案工作基本術(shù)語(yǔ)》對(duì)其的定義表述是:“國(guó)家機(jī)構(gòu)、社會(huì)組織或個(gè)人在社會(huì)活動(dòng)中直接形成的有價(jià)值的各種形式的歷史記錄?!本唧w到建筑工程檔案,是指在建設(shè)項(xiàng)目管理活動(dòng)中形成的原始的、圖物相符的具有保存價(jià)值的真實(shí)記錄和實(shí)際反映,是建設(shè)項(xiàng)目管理在立項(xiàng)、設(shè)計(jì)、施工、使用、維修及改建擴(kuò)建等活動(dòng)中形成的檔案文件。當(dāng)前,隨著建筑業(yè)的快速發(fā)展,工程規(guī)模不斷擴(kuò)大,建筑工程檔案越來(lái)越顯現(xiàn)出其在經(jīng)濟(jì)建設(shè)中的地位及作用,強(qiáng)化與完善建筑工程檔案管理,不僅是提高工程質(zhì)量和管理水平的重要保證,也是加快城市現(xiàn)代化建設(shè)進(jìn)程、構(gòu)建和諧社會(huì)的重要手段之一。
l建筑工程檔案資料的內(nèi)容
1.1基建文件
包括決策立項(xiàng)文件;設(shè)用地、征地、拆遷文件;勘察、測(cè)繪、設(shè)計(jì)文件;工程招投標(biāo)及承包合同文件;工程開工件;商務(wù)文件;工程竣工備案文件;其他文件。
1.2工程監(jiān)理資料
主要包括監(jiān)理合同類文件;監(jiān)理工作記錄;工程的監(jiān)理管理資料;監(jiān)理驗(yàn)收資料等。
1.3施工資料
主要包括施工技術(shù)資料;施工管理資料;施工物資資料;施工測(cè)量記錄;工程施工記錄(包括通用記錄、電梯專用安裝記錄、土建專用施工記錄等);施工試驗(yàn)記錄(包括通用施工試驗(yàn)記錄、土建專用施工試驗(yàn)記錄、設(shè)備試運(yùn)轉(zhuǎn)記錄、管道專用施工試驗(yàn)記錄、電氣專用施工試驗(yàn)記錄、電梯專用施工試驗(yàn)記錄、通風(fēng)空調(diào)專用施工試驗(yàn)記錄等);施工驗(yàn)收資料;竣工圖(主要包括總平面布置竣工圖、建筑工程竣工圖、室外各種管線竣工圖、結(jié)構(gòu)工程竣工圖、裝飾工程竣工圖、給排水工程竣工圖、強(qiáng)電弱電工程竣工圖;通風(fēng)空調(diào)工程竣工圖以及其他特殊專業(yè)工程竣工圖)。
2當(dāng)前建筑工程檔案整理中存在的主要問(wèn)題
雖然基本建設(shè)項(xiàng)目檔案資料管理暫行規(guī)定對(duì)建設(shè)工程檔案編制內(nèi)容及工程圖紙資料都有明確的規(guī)定和要求,但因種種原因,在工程檔案的質(zhì)量及管理中仍存在一些問(wèn)題,主要如下:
2.1檔案材料不全
一些工程項(xiàng)目竣工后無(wú)檔案材料,或只有工程主體檔案,缺少配套工程檔案,地下管線、園林綠化等檔案材料更是沒(méi)有。筆者以為原因如下:一是資料整理較為繁瑣使得一些管理人員很難盡職盡責(zé)地做好;二在工程項(xiàng)目施工中,缺乏專職的檔案管理人員,工程各項(xiàng)資料散存在不同人員手中,當(dāng)施工工程處即將完成時(shí),許多人員都撤離了現(xiàn)場(chǎng),留下的人員對(duì)資料不熟,加之有些資料簽字手續(xù)不完備.還需施工單位或監(jiān)理人員簽字,人員一時(shí)很難找齊,隨著時(shí)間的延長(zhǎng),勢(shì)必造成工程檔案的遺失或因保管不當(dāng)造成檔案的損壞;三是施工單位沒(méi)有按規(guī)定及時(shí)移交工程竣工資料,造成統(tǒng)一管理的時(shí)間延誤,甚至導(dǎo)致工程資料丟失。
2.2檔案資料質(zhì)量低下
一些施工單位對(duì)檔案資料不管優(yōu)劣一概接收,造成一些沒(méi)有保存價(jià)值的資料也進(jìn)入管理環(huán)節(jié),影響了檔案的優(yōu)化管理;項(xiàng)目負(fù)責(zé)人不在現(xiàn)場(chǎng),工作人員隨意代簽,尤其是一些重要性文件如審批文件、竣工圖章的簽字等,影響了檔案保管的期限,也影響了檔案材料的真實(shí)性和法律性;有些工程資料在制作時(shí)數(shù)量不充足,或由于保管不當(dāng),導(dǎo)致資料丟失,使得竣工驗(yàn)收時(shí)有很多資料以復(fù)印件的形式出現(xiàn);有的工程項(xiàng)目檔案工作不按計(jì)劃、步驟實(shí)施,而是在驗(yàn)收前集中突擊編制和整理項(xiàng)目竣工圖及資料,形成事后印文件、補(bǔ)手續(xù)、填數(shù)據(jù)等違規(guī)事實(shí),造成部分項(xiàng)目檔案內(nèi)容失真。
2.3缺乏有效統(tǒng)一的管理模式。
有的單位嚴(yán)格規(guī)范檔案管理工作,成立了專門的檔案室,專人專柜管理,工程檔案管理較好;有的單位則不然,工程檔案由其他業(yè)務(wù)部門代管或由文書檔案員兼管,沒(méi)有達(dá)到標(biāo)準(zhǔn)化、制度化、規(guī)范化要求,檔案規(guī)章制度形同虛設(shè),不但造成工程項(xiàng)目文件很難完整、全面地保存下來(lái),還可能造成文件資料的褪色、霉變甚至遺失。
2.4缺乏復(fù)合型檔案管理人員
檔案管理人員專業(yè)素質(zhì)參差不齊,一部分人員沒(méi)有參加過(guò)專業(yè)知識(shí)培訓(xùn),管理水平較低,服務(wù)意識(shí)差,在工作中處于被動(dòng)應(yīng)付狀態(tài),極大影響了工程檔案的質(zhì)量。當(dāng)前,在建筑領(lǐng)域,資料員由施工員兼職的情況較多,相對(duì)于專業(yè)的檔案員、資料員,他們不熟悉檔案法規(guī)及制度,不清楚具體的歸檔標(biāo)準(zhǔn)、要求,使得工程檔案與建設(shè)工程難以同步形成,導(dǎo)致相對(duì)多的工程檔案在收集過(guò)程中遺失、失真,最終造成工程檔案資料接收時(shí)零散、不全、遺漏、丟失等現(xiàn)象。
3基于實(shí)例的建筑工程檔案管理思考
針對(duì)上述問(wèn)題,下面筆者以某大廈的改造工程為例,就如何實(shí)現(xiàn)檔案管理與工程建設(shè)同步進(jìn)行,有效避免資料管理的混亂分散以及頻繁返工造成人力、物力、財(cái)力的浪費(fèi),確保檔案資料的完整性、系統(tǒng)性與準(zhǔn)確性進(jìn)行總結(jié)。
3.1概況
某多功能商務(wù)大廈建于1989年,框-筒結(jié)構(gòu),占地面積768m2,地下l層,地上12層,局部14層(四個(gè)角部)。本次改建是在12層的屋面上加建2層,與四角的突出部分(14層)平齊,成為一棟完整的14層建筑,并重新裝修外立面。改建總建筑面積1679m2,其中原有建筑面積797m2:,增加建筑面積882m2。
3.2明確管理職責(zé),完善檔案管理工作的質(zhì)量保證體系
從工程建設(shè)項(xiàng)目一開始,即將檔案管理工作納入到整個(gè)工程建設(shè)的管理體系中,下發(fā)一系列相關(guān)文件,明確管理職責(zé),完善檔案管理工作的質(zhì)量保證體系:1)明確各級(jí)、各部門的檔案管理職責(zé)。工程指揮部檔案管理實(shí)行“統(tǒng)一管理、以塊為主、分級(jí)負(fù)責(zé)”的管理模式,建立與工程檔案工作任務(wù)相適應(yīng)的管理機(jī)構(gòu),成立檔案工作領(lǐng)導(dǎo)小組,明確了組長(zhǎng)及領(lǐng)導(dǎo)小組成員,并成立了由總監(jiān)、工程管理部門、檢測(cè)中心主要負(fù)責(zé)人等組成的檔案管理網(wǎng)絡(luò),配備專職檔案管理人員,制定檔案管理制度,統(tǒng)一管理建設(shè)項(xiàng)目的檔案,形成強(qiáng)有力的質(zhì)量保證體系,從源頭把好檔案管理質(zhì)最關(guān);2)明確了施工、監(jiān)理單位必須按照項(xiàng)目文件編制與檔案整理辦法的要求,做好各自職責(zé)范圍內(nèi)檔案的收集、整理、立卷及歸檔;3)明確監(jiān)理單位要切實(shí)負(fù)起監(jiān)理工作的相關(guān)責(zé)任,不僅要監(jiān)理工程,還要監(jiān)督檢查項(xiàng)目文件編制和檔案整理工作。以上管理制度的建立,引起了各單位領(lǐng)導(dǎo)及專兼職人員對(duì)檔案工作的重視,推動(dòng)了檔案工作的開展。
3.3 提高檔案管理人員素質(zhì),保證檔案質(zhì)量
要保證檔案質(zhì)量,提高檔案人員的素質(zhì)是關(guān)鍵一環(huán)。檔案管理人員要做好檔案管理工作,必須了解檔案形成與積累的重要性與及時(shí)性,掌握檔案要求的內(nèi)涵,為此,我們將檔案形成的全過(guò)程及其管理納入檔案管理人員的職責(zé)范圍,尤其強(qiáng)調(diào)施工檢測(cè)實(shí)驗(yàn)記錄等原始資料必須符合歸檔要求,務(wù)必做到線條清楚、字跡工整、數(shù)據(jù)準(zhǔn)確。
3.4 嚴(yán)格考核制度,推進(jìn)檔案工作整體水平的提高
制定考核獎(jiǎng)懲制度及細(xì)則,對(duì)在檔案的收集、整理、檔案管理軟件使用中成績(jī)突出的單位和個(gè)人給予表?yè)P(yáng)及獎(jiǎng)勵(lì),對(duì)未按規(guī)范要求進(jìn)行檔案收集、積累、整理歸檔的,給予批評(píng)和處罰。并通過(guò)考核工作開展比學(xué)趕超,提高工程檔案工作的整體水平。
3.5強(qiáng)調(diào)檔案質(zhì)量,將檔案工作落到實(shí)處
1)嚴(yán)格把好紙質(zhì)檔案的形成、積累、整理與歸檔關(guān),實(shí)施預(yù)立卷制度,必須分類、裝盒、分卷保管。嚴(yán)格過(guò)程控制,注重平時(shí)的積累收集,分門別類地按照文件材料的形成規(guī)律及系統(tǒng)聯(lián)系進(jìn)行歸檔,以保證項(xiàng)目文件編制的歸檔質(zhì)量;2)分別抓好設(shè)計(jì)變更、設(shè)計(jì)變更審簽表收集整理以及竣工圖的編制等重點(diǎn)工作。強(qiáng)調(diào)竣工圖要真實(shí)、準(zhǔn)確地反映工程竣工的實(shí)際情況,編制的竣工圖需附竣工說(shuō)明,務(wù)必準(zhǔn)確、規(guī)范、清晰。要將設(shè)計(jì)變更內(nèi)容一一反映在竣工圖上,施工單位必須在施工圖上注明修改的部分,并附以設(shè)計(jì)變更通知單和施工說(shuō)明;3)將檢查文件材料的形成程序是否規(guī)范、簽署是否完備、歸檔案卷制作質(zhì)量是否精良作為驗(yàn)收的必備條件。強(qiáng)調(diào)各部門盡職盡責(zé)地進(jìn)行檢查控制,檔案管理人員逐卷檢查案卷題名、卷內(nèi)目錄和內(nèi)容是否準(zhǔn)確和規(guī)范,并明確規(guī)定,對(duì)未經(jīng)審查或經(jīng)審查驗(yàn)收未通過(guò)的項(xiàng)目檔案,不得進(jìn)行工程費(fèi)用結(jié)算,不得申報(bào)優(yōu)質(zhì)工程。
3.6 創(chuàng)建符合現(xiàn)代管理理念的檔案管理分類體系
1)按照建設(shè)部《建設(shè)工程文件歸檔整理規(guī)范》規(guī)定的檔案歸檔范圍進(jìn)行案卷的著錄,檔案管理人員在檔案整理歸檔過(guò)程中,根據(jù)擴(kuò)建工程設(shè)置的內(nèi)容、施工工序具體類目,對(duì)應(yīng)歸檔類別進(jìn)行案卷和卷內(nèi)文件著錄,各道工序的檔案歸檔是否準(zhǔn)確、完整、齊全均在控制狀態(tài)中;2)固化工程檔案的分類編號(hào),確定統(tǒng)一的分類號(hào)及標(biāo)識(shí)代號(hào),從而有效地避免分類、編目及標(biāo)識(shí)上的雜亂無(wú)序,體現(xiàn)了檔號(hào)的惟一性。